Below you will find a thorough example of a typical frame inspection that needs to be completed when building your own home. It covers all aspects of the “pre-drywall” inspection that you should perform, and if properly done, will save you time in money during construction.
FRAME INSPECTION
- Headers sized correctly – trimmers in place. Bearing
- Wind bracing – all exterior corners, 25′ on center, secured, no “K” bracing, end gables
- Additional studs below beams. Triples bolted/glued
- Door/window trimmers – installed, proper quality, not too short.
- Joist hangers – proper size, not missing nails, not missing, double angled.
- Stairs – supported, treated below stringers.
- Purlin – correct span, all splices, properly braced, correct angles, sized to rafter, 12″ max span
- Ridges supported – both ends, 12″ on center, splices done properly if required
- Hips supported – both ends, 12″ on center, splices done properly if required
- Valleys supported – both ends, 12″ on center, splices done properly if required, 2 studs/blocks to slab
- Ridges – 2 studs/blocks to slab
- Hips – 2 studs/blocks to slab
- Valleys – 2 studs/blocks to slab; block laydown
- Fireplace – secured, nailers, clearance, raised (if necessary)
- Double joists below water heater / furnace
- Manufactured joist components – squash blocks, blocking panels, rimboards, joist hanger and finger joist blocks installed
- Manufactured joists not damaged – flanges, webs, holes not too large or mislocated
- Plates – nuts / washers, secured within 6″ of splice, and exterior doors, aligned. Treated
- Proper stud spacing – improper splices 36″ required, furred ducts not missing, 16″ OC or 24″ OC as required. Stud blocking tight.
- Walls and columns plumb, cross blocks, twisted. Interior/exterior
- Three blocks at all corners and T’s
- Ceilings installed. Spacing correct and plane properly
- Stiffbacks – blocked and tied, spliced correctly if required, 2×6 upright, installed, not incomplete
- Rat runs – tied at one end, not missing
- Fire stops – stairs, breezeway, dropped ceilings, furr-downs, raked walls, vertical chases all complete
- Sub-floor – Not deteriorated, not loose, no voids, no uneven, 3×3 at top of attic access for landing
- Rafter/joists – Correct span and spacing
- Collar ties – 1/3 distance below ridge, 2×6 used on over 10′ spans – every other rafter
- Chimney – roof clearance, 2 corner studs to slab, flue clearance, secured, baloon framed.
- Bridge blocks – installed, continuous, staggered
- Cabinet blocks – 2×6 required – at 34″ – 54″ – and 84″
- Short walls plumb and square and braced 4 ft on center
- Medicine cabinet – present, 3″ from corners
- Showers vertically blocked for green rock
- Garage door trimmers – insalled, bottom cut at 45 degree, treated or cedar, plumb and not twisted
- Tubs, showers, shelves all installed and level
- Dead wood present – ceilings, angled corners, windows, and columns
- Shower recess aligned with plates, 1″ plate, 1/2″ slab
- Window margins – plumb/level, sides and head, continuous wood product shims
PLUMBING INSPECTION
- No leaks – in supplies or drains
- Pipes inside of walls – not bowing out
- Nail guards installed – All piping, electrical panel attached in garage, freon lines, HVAC and water heater drains all with proper nail guards
- Toilet flanges centered and secured
- Water heater vent secured, 1/2″ clearance at combustibles
- Gas Lines – Installed to all gas appliances. Less than 5′ from appliances
- Shower heads secured with weatherproof screws, 6’6″ above finished shower floor typical
- Stub out for sink drains secured
- Hose bib flanges flush with slab and level
- Clean out flush with slab
- Drain arms have visible fall, blocked within 1/2″ of elbows
- Stud shoes required on all bored studs that exceed the acceptable limit
HVAC INSPECTION
- Primary drain – Fall away from unit, runs to vanity sink, bend required to reduce noise
- Secondary drain – Installed, falling away from pan, exit over window or exterior door
- Furnace vent – Installed, secure, 1″ to 2″ clearance
- Exhaust fan – tubes not crushed or parting – vented to exterior
- Ducts – Installed, secured, complete, supported. Blocked on 3 sides
- Dryer vent – Installed, secured, no breaks, 8″ bottom above brick ledge
- Refrigerant box blocked on 3 sides
ELECTRIC INSPECTION
- Wiring complete – In boxes or stapled to frame inside walls
- Smoke detector – Wired to bedrooms and outside bedrooms
- Garage door openers – Plug and control wires installed
- Security pre-wire – Complete, plug at control box
- Bath fan – Installed, blocked square with walls, taped, wired
- Service – Run to panel location, secured. Home runs through plate, nail guards
- Phone / CATV – Installed, not touching vent pipes, not in return air chase
- Ground wire run – Service plumbing
- Wires insulated from water supply lines. Sleeves through brick
- Recess fixture too close to combustibles
INSULATION INSPECTION
- Sheathing attic space
- Sheathing pony walls
- Block joint spaces
- Seal exterior sheathing
- Block vertical chases
CORNICE/DECKING
- Siding – Installed, smooth, nail butt joints, nails flush and snug. No staples. Z-flashing 4×8, not bowed, not wavey
- Fascia – installed, straight, nailed properly, shingle mold. Touches shingles, level eyebrow
- Soffit – Installed, tight joints, complete, primed
- Brick frieze – Installed, level and plumb, complete
- Soffit vents – Installed, tight joints, smooth, continuous sides/rear, louvered fronts
- Windows – Installed, flanges nailed 16″ on center sides, 12″ on center top and bottom, plumb and level
- Windows flashed – not missing, 1/4″ overhang, above wood trim
- Exterior doors – Installed, long screws used, operate correctly, construction locks installed
- Sheathing – Nailed 12″ on center perimeter, 12″ on center in field, no bridge nailing, installed, repair, no staples, raw wood covered
- Pony brick ledges – inside and outside corners, windowsill
- Sheathing penetrations – sealed with metal tape
- Decking – Installed, level with shingle mold, nailed properly
- Decking support – Clips, 2 each with 1/2 clips per unsupported sides, nail 6″ on center butt joints, 12″ on center in field
- Poly on all windows
JOB SITE INSPECTIONS
- Address clearly posted – required for city inspections
- Job site cleaned – exterior and interior
- Trash bin present – bin and barrel
- Post Tension Cables stressed
- Quality finish on foundation. Honeycombs grouted
- Form material removed
- Safety rails installed on second floors
- No broken glass (safety issue)
ROOFING INSPECTION
- Shingles dried-in, straight, and flat
- Roof jacks – Installed, (3) nails, vent min. 6″ above boot
- Cap and collar installed, metal jack, water heater, and furnace
- Flashing – roof/chimney flashing installed, cap, spark arrestor
- Sky lite – Installed, tried in, level, square, plumb
- Roof plane – no sags or crowns
- Ventilation – ridge vents, air hawks and no dead space in attics
Please understand that this is not a “complete” inspection as should be performed by city and third party inspectors. While this is thorough and should be performed before pre-drywall, it is also important to get an inspection from a third-party. But for the purpose of building your own home, this list should give you insight into the depth of this stage (which is the most important.) If you have any questions regarding this list or particular items, feel free to ask them in the comments below.








{ 1 comment… read it below or add one }
What would be the cost for a pre-drywall inspection in Richmond TX?